A Leading Provider of Building Commissioning
& Facilities Maintenance Related Services

Projects

Educational Facilities

Oak Harbor High School

Location: Oak Harbor, Washington

Description: A two-phased high school addition and modernization. Phase 1 was an addition of an approximately 29,000 square foot wing to include shops and classrooms. Phase 2 was the modernization of three wings and the Field House totalling approximately 203,000 square feet.

WCG Scope: Commissioning per Washington’s Sustainable Schools protocol to include OPR development, design and construction document reviews, commissioning specifications development, submittals review, commissioning plan development, commissioning meetings and site observations, installation verification, functional testing with back-checks, TAB verification, issues tracking, maintenance & building staff training verification, post occupancy review and evaluation with energy analysis and surveys, and final commissioning report production.

Owner: Oak Harbor School District

Completed: 2011